West Spruce Street Grind down and paving Pave West Spruce

Project Description

West Spruce will be paved from South 4th Street to the Cemetery.  Plans can be changed do to weather, material delays, and engineering.

Documents

Project Progress

Project Timing

  • Start
    May 01 2017
  • End
    May 31 2017

05/01/2017 05/31/2017

100%

Overall Project Completion

  • Grind Down Street

    20%
  • pave Entrance Points

    60%

  • 40%

    Install new Curves

  • 80%

    Pave Spruce

20%

Grind Down Street

40%

Install new Curves

60%

pave Entrance Points

80%

Pave Spruce